 Home : Construction of Highways & Roads
Cihanbeyli-Kulu Junction Road bituminous hot-mix pavement construction / Konya
General Directorate of Highways 
Project:
Construction of 90Km road of concrete asphalt layer

Contract Dates:
14.09.92 to 15.05.10

Cost:
US$95.700.
860.-

Construction of 2nd and 3rd section of Antalya-Alanya Express Way / Antalya
General directorate of Highways

Project:
Construction of 65Km of a complete express way.

Contract Dates:
07.11.96 to 15.12.09

Cost:
US$382.632.
004.-

 

Construction of 4th section of Antalya-Alanya Road / Antalya
General directorate of Highways
Project:
Construction of 32Km of a complete express way.

Contract Dates:
16.04.98 to 01.06.06

Cost:
US$111.957.
595.-

 

Construction of Neşetiye group bridges / Aydın
General directorate of Highways

Project:
Construction of four(280m) road bridges.

Contract Dates:
16.11.95 to 31.12.98

Cost:
US$4.719.
826.-

  MÖN Construction & Trade Co.  Tel:(90)(312) 446 38 90 / Fax:(90)(312) 446 47 91